skip navigation

Developing the New Field - Fall 2021 - Summer 2022

Developing the New Field - Fall 2021 - Summer 2022

Photos taken during the construction.
https://cdn1.sportngin.com/attachments/photo/0874-164589332/tempImageu1OTBy_thumb.png
  • June 2021

  • June 2021

  • Work starts - Mid-September

  • Crops removed - Mid-September

  • Entrance - September 23

  • Overview - September 28

  • Burn pile - September 28

  • Shack Nouveau - October 5

  • Site of the New Pavilion - October 5

  • North to the Shack - October 5

  • NE Corner detail - October 5

  • Pavilion Site - October 12

  • Week 3 - October 12

  • Checking Grade - October 12

  • Driveway - October 19

  • Parking Area - October 19

  • Pavilion Site - Week 4-October 19

  • Parking w/ Surface - October 27

  • Utility Poles - October 27

  • Pavilion site + Utility Poles - October 27

  • Seeded - October 27

  • Entrance + Concrete - October 27

  • Driveway in progress - November 2

  • Driveway + Parking - November 2

  • Entrance is Ready - November 2

  • CU Power cables - November 9

  • Driveway is Ready - November 9

  • CU poles installed too close to touch line - November 15

  • Prepared Driveway week 8 - November 15

  • Working the Practice Area - November 15

  • Driveway Almost Finished - November 15

  • Great Work - November 15

  • New road - November 23

  • Road to Pavilion - November 23

  • Fence posts + Pavilion Road - November 23

  • Overview - November 23

  • Entrance gates - November 30

  • Secure Fence - November 30

  • Pavilion Pad - November 30

  • Pitch 1 - December 6

  • Preparing for the Pavilion build - December 22

  • Access Road to Pavilion - January 5

  • Now Just One Utility Pole - January 14

  • Pavilion Door Posts - January 26

  • Ready To Start the Slab - January 27

  • 200 Ft Concrete Pad - January 31

  • Laying the Pavilion Slab - January 27

  • Starting the Pavilion - February 9

  • Building the Pavilion - February 9

  • Field Repair required - January 14

  • Pavilion Framing - March 1st

  • Floodlights + Pavilion Framing - March 9th

  • Pavilion Framing Complete - March 16th

  • Well now Installed - March 25th

  • Blue Metal Roof On - April 19th

  • The Hall of Fame Wall - 23rd April

  • APavilion almost complete - April 24th

  • Pavilion w/ Storage Door - April 7th

  • Pavilion Lighting - May 10th

  • Pavilion Completed - May 13th

  • Safety check - June 15th

  • Safety check - June 15th

  • Overview - June 25th

  • Pavilion at Night - July 7th

  • Night Lights - July 7th

  • Pavilion with Signage - July 12th

  • Matt Wilson Pavilion - July 12th

  • Paver Project Underway - August 18

  • 2 Pitches with Posts - August 18

  • Pitch 1 and Posts - August 18

  • Problems with the Well - September 2

  • One Year Later - 19 September

  • Shed Roof Repaired - 14 December

Loading…

Developing the New Field - Fall 2021 - Summer 2022

Photos taken during the construction.